Skanska has signed a contract with the New York City Department of Design and Construction to design and build the East Side Greenway 14th Street Connector, a new over-water path along Manhattan's East River. The company valued the design-build contract at about $163 million and said it will count toward its U.S. order bookings for the fourth quarter of 2026.

The project replaces a narrow stretch of path beside the FDR Drive, known locally as the "pinch point," between East River Park and Captain Patrick J. Brown Walk. It is one of the last gaps in Manhattan's East River greenway. The new connector will be wide enough for two-way pedestrian and bike traffic, and the early design includes seating, lighting, drinking fountains and waste receptacles.

Skanska and its design partner, Claire Weisz Architects (WXY), will design and build the foundations, piers and structural superstructure for the new segment over the river. The team will also tie the work into existing waterfront infrastructure and utilities next to Con Edison facilities. DDC has said the City will work with Con Edison to keep the East River Generating Station at 14th Street and Avenue C running during the job. DDC is managing the project for NYC Parks and the NYC Department of Transportation.

Design engagement, including community meetings, is set to start soon. Groundbreaking is expected in early 2028, with completion targeted for the end of 2030.

DDC first named the Skanska and WXY team as the apparent selected proposer in June. The agency says design-build will bring the project to completion about two years sooner than traditional design-bid-build. "Using design-build alternative delivery for this project allows us to move forward quicker when doing this type of infrastructure work with 'best-value' for the City," DDC Commissioner Paul A. Ochoa said at the time.

What it means for hiring

Building over the water next to a live highway and a working power plant takes marine and heavy civil superintendents, plus project managers who can run design and construction at the same time. Design-build also pulls hiring forward. Teams on jobs like this need design managers, estimators and preconstruction staff long before the first pile goes in, and New York contractors are competing for the same people across a busy waterfront and infrastructure pipeline.

Source: Skanska https://www.skanska.com/us/en/media/press-releases/2026/skanska-to-deliver-east-side-greenway-14th-street-connector-project-in-new-york-city